Problem Set 10 (Planning The Project) 2023 Business Finance

2023 Earned value analysis A project budget calls for the following expenditures Task Date Budgeted Amount Build

 

Earned-value analysis. A project budget calls for the following expenditures:

Task

Date

Budgeted Amount

Build forms

April 1

$10,000

Pour foundation

April 1

$50,000

May 1

$100,000

Frame walls

May 1

$30,000

June 1

$30,000

Remaining tasks

July 1 and beyond

$500,000

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

We give our students 100% satisfaction for their assignment, which is one of the most important reasons students prefer us from other helpers. Our professional group and planners have more than ten years of rich experience. The only reason that our inception days, we have helped more than 100000 students with their assignments successfully. Our expert’s group have more than 2200 professionals of different topics, and that not all; we get more than 300 jobs every day more than 90% of the assignment get the conversion for payment.