September – December 2023 problem 16-18
Business & Finance
2.value:5.00 pointsProblem 16-18The Budd Gear Co. specializes in heat-treating gears for automobile companies. At 8:00 a.m., when Budd’s shop opened today, five orders (listed in order of arrival) were waiting to be processed.OrderOrder Size(units)Per Unit Time inHeat Treatment(minutes/unit)Due Date(min. from now)A164160B612200C103180D810190E41220a.If the due date rule is used, what sequence should be used?The sequence is.b.What will be the average job tardiness? (Round your answer to 2 decimal places.)Average job tardinessnew average job tardiness is [removed] minutes.